第8部分:配网工程
电缆防火封堵作业指导书
编码:DLFHFD-01
目次
1适用范围······················································································································································145
2编写依据······················································································································································145
3作业流程图···················································································································································145
4安全风险辨析与预控···································································································································145
5作业准备························································································································································13
6作业方法··························································································································································6
7质量控制措施及检验标准·······························································································································9
1适用范围
1.1电压等级
35kV及以下配网工程。
1.2电气类别电缆密集场所或可能着火蔓延而酿成严重事故的电缆线路。
2编写依据
表2编写依据
| 序号 | 引用资料名称 |
| 1 | GB50168—2006《电气装置安装工程电缆线路施工及验收规范》 |
| 2 | GB50217—2007《电力工程电缆设计规范》 |
3 | DL/T5161.5—2002《电气装置安装工程质量检验及评定规程第5部分:电缆线路施工质量检验》 |
| 4 | Q/CSG11105—2008《南方电网工程施工工艺控制规范》 |
| 5 | GB0229—2006《火力发电厂与变电站防火规范》 |
| 6 | DL5027—1993《电力设备典型消防规程》 |
| 7 | 《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》 |
4安全风险辨析与预控
图3作业流程图
4.1电缆防火封堵作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2按《指南》中与电缆防火封堵作业相关联的《电网建设安全施工作业票》(编码:
DLFHFD-01-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须
重新办理作业票,在工作完成后上交项目部保存备查。
表4.1作业任务安全基准风险指南
| 序号 | 危害名称 | 风险种类 | 风险等级 | 风险控制措施 |
1 | 电缆隧道内施工,通风不足 | 窒息 中暑 中毒 | 中等风险 | 电缆隧道内应有可靠的通风设施,必要时增加排风扇,加强通风效果 |
2 | 电缆隧道内施工,照明不足 | 坠落摔绊碰撞淹溺 | 中等风险 | 1.电缆隧道内应有足够的照明设施; 2.隧道内所有孔洞应有围栏或防护措施 |
3 | 使用有缺陷的梯子 | 坠落碰撞 | 中等风险 | 1.使用合格梯子; 2.梯子上工作时应跷脚,与地面夹角以60°为 宜; 3.不得手持重物上下梯子; 4.梯子应有防滑措施; 5.设专人扶梯 |
4 | 防火封堵作业不戴工作手套 | 灼(烫)伤 | 可接受的风险 | 防火封堵作业必须戴工作手套 |
5 | 稀释剂现场随意摆放 | 灼(烫)伤窒息 | 低风险 | 1.稀释剂必须使用密封的金属容器充装到现场使用,使用完余下的必须马上回收并注意密封存放; 2.现场配备数量充足、有效的消防器材 |
6 | 施工区域防暑降温措施不足 | 中暑 | 中等风险 | 1.避开炎热时间段作业; 2.配置太阳伞,配置风扇; 3.及时补充水分; 4.现场配备应急药品 |
5.1作业前施工条件
表5.1作业前施工条件
| 序号 | 项目 | 内容 | 确认人 | 说明 |
1 | 任务单 | 根据本单位实际设置内容(包含本项工作) | 本工序施工负责人 | 经审批 |
2 | 图纸 | 设备变更单、设计图纸 | 本工序施工负责人 | 经审批 |
3 | 预算材料表 | 主、辅材料 | 本工序施工负责人 | 经审批 |
4 | 施工方案 | 施工措施、安全技术交底(项目部级) | 本工序施工负责人 | 经审批 |
5 | 相关证照 | 根据需要办理涉及进入工作场所的手续、证件 | 本工序施工负责人 | 有效 |
表5.2人员、主要工器具及仪器仪表配置
| 序号 | 项目 | 内容 | 说明 |
1 | 人员配置 | 根据工程量的大小配备足够施工人员。施工现场明确施工负责人、技术负责人、质安员、安装施工作业人员组织到位 | 所有人员必须持有与专业相对应的上岗证(重要的消防设施安 |
| 装须外委有消防资质证的施工单 位),辅助工不得从事电气设备安 装等专业工作 | |||
2 | 施工内容相对应的材料 | 防火隔板、防火涂料、防火包、防火带、防火堵料等 | (1)有资质的检测机构出具的检测报告。 (2)出厂质量检验报告。 (3)产品合格证 |
3 | 施工内容相对应的机械、工器具及仪表 | 工器具:排气扇、油扫、钢锯、尺子等 | 根据施工现场的需要自行决定工具数量 |
4 | 完成开工程序 | 工作负责人向项目负责人报开工,由项目负责人完成向监理单位开工报审手续 | 施工准备完成可报开工,当施工准备不足时,上报该项目负责人协调解决 |
表6作业方法
| 序号 | 项目 | 内容 | 说明 |
1 | 作业前工作 | (1)现场施工负责人向进入本施工范围的所有工作人员明 确交待本次施工设备状态、作业内容、作业范围、进度要求、 特殊项目施工要求、作业标准、安全注意事项、危险点及控 制措施、危害环境的相应预防控制措施、人员分工并签署(班 组级)安全技术交底表。 (2)工作负责人负责办理相关的工作许可手续,开工前做 好现场施工防护围蔽警示措施,夜间施工的,须有足够的照 明。 (3)现场施工负责人检查确认进入本施工范围的所有工作 人员正确使用劳保用品和着装,并带领施工作业人员进入作 业现场。 (4)在带电运行区域内或邻近带电区域内进行防火施工时,应有可靠的安全措施 | 按安规规定统一着装,佩戴安全帽,佩戴有个人照片的作业证(或胸卡证) |
2 | 开始主要作业 | 现场施工负责人发出许可开工命令 | |
3 | 作业程序 | 现场施工负责人正确、安全地组 织作业,现场施工质安员负责现场 作业全过程的安全、质量监控 | |
4 | 安装防火隔板 | (1)施工前,清理现场除去油垢、灰尘和杂物。在场外检查防火隔板应平整、美观、无裂缝、破损并按量测尺寸事先准备好防火隔板。 (2)施工中,如需搬动电缆时,应有安全措施和监护。安 装防火板接缝要重叠 | |
5 | 浇注防火涂料 | (1)涂刷前,清理电缆表面除去油垢,灰尘和杂物。搅拌涂料,使粉末沉淀物与液体混匀。 (2)涂刷时,涂料的恩氏黏度以100s为宜,若过稠,应调 和稀释剂(200号溶剂汽油或松香水),以确保涂料均匀附着 被涂物。 (3)多次涂刷,每间隔4h可涂刷一次,直至涂层厚度达1mm 左右为止。 (4)涂刷时,应注意:涂料溶剂为挥发性易燃物,施工时 应严禁火种和加强通风。严防水分进入涂料,使涂层结皮、 龟裂。未用完涂料,应重新封严,以利再用 | |
6 | 填充防火包 | (1)施工前,清理现场除去油垢,灰尘和杂物。量测封堵点的尺寸计算封堵体积,作为估算防火包用量的根据。估算 |
| 时,应满足:相邻两层防火包的接缝应错开,防火包叠放的 总尺寸与封堵口的尺寸吻合。 (2)防火墙叠放,墙基应清除积水、填平水坑,然后分层 错缝叠放。 (3)电缆交叉点封堵叠放,将交叉电缆分层理顺,自下而 上,理顺一层电缆,叠放一层防火包,注意各层防火包接缝 错开。 (4)电缆桥架防火包叠放,所保护桥架电缆,通常靠近热 源或泄口压口,应在迎向热源一侧,分层错缝叠放防火包, 务求严密 | |||
7 | 包裹防火带 | 一般在使用防火涂料处理有困难的电缆线路上和电缆接头两侧及相邻电缆2~3m长的区段施加防火包带。包带在绕包时,应半叠绕包两层及拉紧密实即可 |
7.1质量控制措施
7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。
7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗
证。
7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治措施。
7.1.4作业现场必须有经审核批准的设计图纸和施工方案,作业人员必须按图施工。
7.1.5施工质量检验一般按以下方式进行。质量检验一般采用三级检验制,施工队(组)对所施工的分项工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜
低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。
7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。
7.2检验标准
质量检验按《10kV~500kV输变电及配电工程质量验收与评定标准第8册:配网工程》中的Q/CSG表
8-7.4要求执行。
●附件1安全施工作业票
编码:DLFHFD-01-01/01
| 工作时间 | 工作地点 | 技术员 | 现场安全员 | 现场负责人 | |||
| 安全风险分析及控制措施 | |||||||
| 序号 | 危害名称 | 风险种类 | 风险等级 | 风险控制措施 | |||
1 | 隧道内施工,通风不足 | 窒息、中暑、中毒 | □中等风险 | 现场作业应严格执行相关安全规程及安全技术措施,并重点关注但不限于以下措施: □电缆隧道内应有可靠的通风设施,必要时增加排风扇,加强通风效果。 □电缆隧道内应有足够的照明设施。 □隧道内所有孔洞应有围栏或防护措施。 □使用合格梯子。 □梯子上工作时应跷脚,与地面夹角以60°为宜。 □不得手持重物上下梯子。 □梯子应有防滑措施。 □设专人扶梯。 □防火封堵作业必须戴工作手套。 □稀释剂必须使用密封的金属容器充装到现场使用,使用完余下的必须马上回收并注意密封存放。 □现场配备数量充足、有效的消防器材。 □避开炎热时间段作业。 □配置太阳伞、风扇。 □及时补充水分。 □现场配备应急药品 | |||
2 | 隧道内施工,照明不足 | 坠落、摔绊、碰撞、淹溺 | □中等风险 | ||||
3 | 使用有缺陷的梯子 | 坠落、碰撞 | □中等风险 | ||||
4 | 防火封堵作业不戴工作手套 | 灼(烫)伤 | □可接受风险 | ||||
5 | 作业现场随意摆放稀释剂 | 灼(烫)伤、窒息 | □低风险 | ||||
6 | 施工区域防暑降温措施不足 | 中暑 | □中等风险 | ||||
| 安全补充事项/平面布置图 | |||||||
| 现场接受交底人员签名 | |||||||
| 备注 | |||||||
并宣读。(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变
更时,应在备注栏记录变更情况。对新增人员进行交底,并签名确认。(三)应根据现场条件、范围和环境,补充安全事项或平面布置图。(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。(五)基准风险等级与风险控制措施在开工前现场打“√”。(六)签名不齐全(含代签名的)均作废票处理。下载本文