1. Job diaries are subjective accounts of what occurred during the
course of the construction workday. True or false?T
工作日记是建造工作日的过程中发生了什么的主观账户
2. An RFI is a formal request for information necessary to help clarify
construction operations. True or false?T
一个RFI是正式要求必要的信息,以帮助阐明施工作业。
3. Weather information is typically reported on a daily report. True or
false?T
4. Meeting minutes are confidential documents kept internally within
the organization that recorded them. True or false?F
会议纪要属于机密文件,内部保持该记录他们在组织内
5. What is the name of the document that authorizes the start of
construction?B
a. Notice of award
b. Notice of proceed
c. Notice of agreement
d. Notice of intent
e. None of the above
6. Which of the following is not an example of a project submittal?B
a. Product data
b. Addenda
c. Shop drawing
d. Material samples
7. What does the Hyatt story illustrate?C
a. The important of proper hotel architecture
b. The important role of engineering in the design/build process
c. The importance of thoroughly reviewing shop drawings
d. The importance of building codes
8. What is the traditional percentage used for owner retainage?Ca. 5
b. 8
c. 10
d. 15
e. 20
9. Obtaining lien waivers protects the owner in which of the following
ways?A
a. It prevents paying for work that has not been completed.
b. It helps prevent overcharging.
c. It protects the owner from subject to a mechanic’s lien.
d. It prevents duplicate or fraudulent invoices.
e. All of the above are correct.
10. Which of the following is not the normal reason for a change in a
lump-sum or fixed price contract?B
a. Differing site or unforeseen conditions
b. Delays caused by contractor inactivity
c. An increase or decrease in owner requirements
d. An error in the design documents
11. In a typical application for payment, the contractor has the option of
submitting back-up information separately from application. True or
false?F
在典型应用中支付,承包商已经从应用程序中单独提交备份信息的选项
Exercise
1. Investigate the specification for a project that you are familiar with
and prepare a list of all of the submittals required. Note the
recipient of each submittal. How many copies are required for each?
How many days are allotted for designer review? Owner review?
2. Prepare the meeting minutes for the next meeting you attend. (This
may or may not be school-related.) Investigate the different forms
that companies use to prepare minutes and adopt the form you feel
is best.
3. Visit a local project or companies and research a resent change thathas occurred. Answer the following questions:
a. What is the nature of the change?
b. What cause the change?
c. How was the change identified? By which party?
d. How long did it take for the change to be resolved?
e. What was the impact of the change on the project’s scope,
budget, and schedule下载本文