视频1 视频21 视频41 视频61 视频文章1 视频文章21 视频文章41 视频文章61 推荐1 推荐3 推荐5 推荐7 推荐9 推荐11 推荐13 推荐15 推荐17 推荐19 推荐21 推荐23 推荐25 推荐27 推荐29 推荐31 推荐33 推荐35 推荐37 推荐39 推荐41 推荐43 推荐45 推荐47 推荐49 关键词1 关键词101 关键词201 关键词301 关键词401 关键词501 关键词601 关键词701 关键词801 关键词901 关键词1001 关键词1101 关键词1201 关键词1301 关键词1401 关键词1501 关键词1601 关键词1701 关键词1801 关键词1901 视频扩展1 视频扩展6 视频扩展11 视频扩展16 文章1 文章201 文章401 文章601 文章801 文章1001 资讯1 资讯501 资讯1001 资讯1501 标签1 标签501 标签1001 关键词1 关键词501 关键词1001 关键词1501 专题2001
FG2500 standard spec
2025-10-05 23:18:48 责编:小OO
文档
C.B.K.M. Flip Chip Bonder (FG2500)

Customer:

Project name:

Flip Chip Bonder Line

Line/Equipment name:

FG2500

Drawing/Document title:

Standard Specifications

Date: September 19, 2003

Toray Engineering Co., Ltd.

Installation site:

Construction/Manufacturing

No.

Document No.

60Q000-001

SUBMIT TO DIVISION

Customer 2 <3>SIGNATURE

DATE

For return 1

<2> PRED'D Copy

<1>

CHK'D

TOTAL

3

REV: NO.

DATE

DESCRIPTION

PREP'D

CHK'D

APP'D APP'D

1. Equipment outline (2)

1-1. Dimensions (2)

2. Specifications (3)

2-1. Work components (3)

2-2. Bonding area and recommended marks (6)

2-3. Equipment capability (7)

2-4. Operations and utilities (9)

2-5. Detailed specifications of each unit (11)

2-6. Equipment engineering conditions (14)

2-7. List of delivery items to customer (15)

3. Division of responsibilities (17)

3-1. Responsibilities belonging to TORAY (17)

3-2. Responsibilities not belonging to TORAY (17)

3-3. Customer’s supplies (18)

3-4. Others (18)

4. Acceptance conditions (19)

4-1. Alignment accuracy (19)

4-2. Cycle time (19)

4-3. Operating efficiency check (19)

5. Warranty coverage (21)

5-1. Warranty period (21)

5-3. Troubleshooting (21)

5-4. Limit of responsibility (21)

6. Handling (23)

Note: SI unit system is used in this specification document. However, unit from non-SI system will also be placed, next to values described by SI unit, whenever necessary.

1. Equipment outline

The FG2500 is a semi-automatic bonder for bonding LSI or FPC on substrate (LCD or FPC). With this semi-automatic bonder, the equipment automatically takes up substrate (LCD or FPC) and LSI or FPC from tray or pallet. The equipment, then, aligns the position of substrate (LCD or FPC) with LSI or FPC.

Operator, however, is to place pallets of substrates (LCD or FPC) and pallets of LSI trays or FPC, manually, onto the loading unit. Operator, also, is to unload substrates (LCD or FPC), manually, from the conveying unit.

1-1. Dimensions

A•F 4093mm E •F 1965mm I•F 460mm M •F 1500mm B•F 1753mm F •F 1490mm J•F 1100mm C•F 615mm G•F 843mm K •F 400mm D•F 670mm H•F 1303mm L •F 253mm Remarks: There is a possibility of making changes of the above dimensions.

F

Size Unit: mm Min. 27 (L) × 27 (W)

Max. 130 (L) × 130 (W)

t=0.4 ×2 to 1.1 ×2

Any dimensional deviations or

curves which may have bad

influence on conveyance must

be avoided.

Polarizer thickness Unit : mm When measurement function of the polarizer thickness is used : Max. 0.7

When measurement function of the polarizer thickness is not used : Max. 1.5

1Substrate

(for COG)

Material Glass (LCD)

Size Unit: mm LCD dimension

Min. 27 (L) × 27 (W)

Max. 110 (L) × 130 (W)

t=0.4 ×2 to 1.1 ×2

FPC + LCD

Max. 130•~130

However, if FPC size is small,

large-sized substrate can be

used.

(Please refer to figures on Page

5)

Any dimensional deviations or

curves which may have bad

influence must be avoided.

Polarizer thickness Unit : mm When measurement function of the polarizer thickness is used : Max. 0.7

When measurement function of the polarizer thickness is not used : Max. 1.5

1’Substrate

(for FOG)

Material Glass (LCD)

Size Unit: mm Min. 27 (L) × 27 (W)

Max. 100 (L) × 100 (W)

t = Min. 0.02

There should not be any bend

or

wrinkles which may have bad

influence on vacuuming,

transportation and image

recognition.

•¨•@T est will be necessary with

actual substrate material for

the above confirmation.

The distance from the film

edge to the bonding center is

50 or less.

1”Substrate

(for COF)

Material Polyimide (FPC)

1’’’Substrate

pallet Size

Unit : mm252(L)•~190(W)Please refer to figures on Page 5 Size

Unit : mm

Width: 1.0 to 6.5

ACF laminating length : 3 to 68

Width can be adjusted within

the range between 1 to 6.5 mm. Quantity of

ACF heads

1 (or 2)Choice of

2 ACF heads is

optional.

Number of

ACF types 1 (or 2)

If 2 ACF heads is chosen,

laminating 2 kinds of ACF

is possible.

Locations of

ACF

lamination

1•`32/substrate

2ACF

Supplier Hitachi Chemical Sony Chemical s

Size

Unit: mm Min. 3.0 (L) × 1.0 (W)Max. 30 (L) × 5 (W)t = 0.35 to 0.95Regarding LSI which is smaller than 1.0mm, test will be

necessary with actual material for the confirmation.Quantity of LSI types

1 or 2

Refer to Note 3. on this page

Locations of LSI

1•`32/substrate Supply

orientation

Face-up or face-down

Tray 2 , 3 or 4 inch waffle tray can be

used. However, pallets

corresponding to tray sizes are required.Allowable clearance of LSI within a tray pocket:

Within 0.2 mm

3

LSI

(for COG,COF)Tray pallet size

Unit: mm

252(L) × 190 (W)

Please refer to figures on Page 5Size

Unit: mm

Min. 25 (L) ×20 (W)Max. 60 (L) ×60 (W)t = Min. 0.02

There should not be any bend or wrinkles which may have bad influence on vacuuming,transportation and image recognition.

•¨ Test will be necessary with actual material for the confirmation.

Length of bonding head is Max.60mm. Accordingly, the effective bonding length is 58mm.

Quantity of FPC types

1

Locations of FPC to be bonded 1•`32/substrate Supply orientation Face-up or face-down

3’

FPC

(for FOG)

Pallet size Unit: mm

252(L) × 190 (W)

Allowable clearance of FPC within a pallet pocket:Within 1.0 mm

Please refer to figures on Page 5

Note

1. Jig sets corresponding to substrate type and size are required.

2. In case of two-sided bonding, two passes are required.

(This machine is not equipped with the table that rotates by 90degrees.)

Please refer to figures on Page 5

3. In case of LSI bonding of 2 kinds, the following conditions are required. Also, special jig set corresponding to LSI length is required.

X 2.0 mm, and

X = ( L1 - L2 ) /2 + 1.8 mm

In case of T1

T2

X 2.0 mm

In case of ( T1 + 0.1mm ) < T2

The process below is possible. 1st product (1st pass)

2nd product (2nd pass)

The process below is not possible.

unit:mm

If FPC size is small, large-sized substrate can be used.

(Example)

Loading ACF laminating Pre-bonding Main

-bonding

Loading

90•‹rotation

90•‹rotation

Main-bonding

90•‹rotation

7mm or over (Required)

(Better)

3mm of any substance inside the pallet may be kept above the dotted line.

2-2. Bonding area and recommended marks

Allowable range

Application Items

COG FOG COF Bonding area (X)A Max.60 mm 55 mm 45 mm Bonding area (Y)

B Max.10 mm 10 mm 50 mm Substrate mark recognition area (X)

C Max.36 mm 36 mm 36 mm Substrate mark recognition area (Y)

D Max. 2 mm 2 mm 2 mm LSI/FPC mark recognition area (X)

E Max.30 mm 30 mm 30 mm LSI/FPC mark recognition area (Y)

F Max. 5 mm 5 mm 5 mm Substrate marks for bonding (outside of ACF application area, two black circles with white inside)

G Min.ƒÓ0.1 mm ƒÓ0.1 mm ƒÓ

0.1 mm LSI/FPC marks for bonding H Min.ƒÓ0.1 mm ƒÓ0.1 mm ƒÓ0.1 mm Substrate marks for transportation ‚h Min.ƒÓ0.5 mm ƒÓ0.5 mm ƒÓ0.5 mm ACF lamination area

K

Min.

0.4 mm

0.4 mm

-------------

*This is based on the assumptions that there shall not be any trouble resulting

from the dimensional accuracy of materials supplied by customer.

The substrate marks must be positioned within the area marked with slanting lines in the illustration under the following conditions.

l The substrate marks, which are in the form of •@a black circle with white inside and a diameter of “G”, are positioned in two places outside of the ACF application area within the above area.l There must be no dirt, scratches or foreign objects on the substrate surface, and there must be no chromatic changes in the view.

The FPC marks must be positioned within the area marked with slanting lines in the illustration under the following conditions.

l The FPC marks, which can either be a black circl with white inside or a white circle with black inside, both having a diameter of “H”, are positioned in two places.

l There must be no dirt, scratches or foreign object on the substrate surface, and there must be no chromatic changes in the view.

Substrate marks Y

errors from measurement should not

exist.

Note : The above features are applicable only when appropriate work components are used.

Work components should not cause problems during transfer, alignment or bonding.2-4. Operations and utilities

Installation

site Floor strength: 1000 kg/m2 or higher

Atmosphere Class 10,000 clean room

Environment Temperature: Room temperature (23±3°C)

Humidity: 60% RH ±10% (No condensation)

Vibration: There must be no severe vibration

that affects positioning.

These

environmental

conditions must be

met at least 4 hours

before the operation

start.

Operating conditions

Maintenance space Allow sufficient clearances around the equipment for operation and maintenance. (1 meter each to the front, rear, right and left of the equipment.)

Installation

site

Floor strength: 1000 kg/m2 or higher Atmosphere Class 10,000 clean room

Storage

conditions

Environment Temperature: Room temperature (23±3°C) Humidity: 30 to 80%RH (No condensation) Vibration: There must be no severe vibration

that adversely affects the

equipment.

Power requirements 1-phase, 220 V +/- 10% 60/50 Hz +/- 1 Hz or

3-phase, 220 V +/- 10% 60/50 Hz +/- 1 Hz

(Prepare a power source with 50A or less breaker

for safety)

10 KVA, grounded in accordance with all

relevant local ordinances and regulations (100

Ħgrounding resistance or lower).

Prepare a power source that produces no instant

stops or electrical noise.

Since the equipment uses many servomotors,

the leakage current level is comparatively high.

An earth leakage breaker with a sensitivity

current of 100 mA is mounted on the power

distribution board.

For safety, grounding with a 100Ħor lower

resistance must be performed.

If the voltage fluctuation range exceeds +10%,

the equipment may be damaged.

If the nominal power supply voltage exceeds the

above mentioned range, an optional step-down

transformer can be provided with some charges

on customer. Inform Toray of the voltage value

and the power transmission status (such as Ģ-

Y).

*Concerning any

power supply

requirements

other than those

noted to the left,

consult with Toray

in writing before

the specifications

are confirmed.

*If a step-down

transformer

is necessary,

Toray is to

prepare one with

some charges on

customer.

Air pressure source Dry air: 0.49 - 0.59 Mpa

Approx. 800 L/min. depending upon the air blow rate.

Utilities

Vacuum source Vacuum exhaust rate: 480 L/min.

Ultimate vacuum: – 80 kPa ( – 600 mmHg)

A vacuum source with a higher level than those

listed above must be prepared.

Vacuum pump is

optional.

Equipment dimensions (Without cleaning unit and excluding the signal

light and monitor)

Approx. 3423 (W) × 1753 (D) × 1550 (H)

Unit: mm

(Including the height of signal light and

monitor )

Approx. 3423 (W) × 1753 (D) × 1900 (H)

Unit: mm

These dimensions

do not include the

working space.

Equipment

weight Approx. 3000kg (Without cleaning unit)Cover and frame: 7.5Y9/1 (Munsel color Color

system), semi-gloss

PVC section: Clear (antistatic plate)2-5. Detailed specifications of each unit Substrate transfer unit

Loading unit

(Pallet type) 1 set Substrates are supplied from pallet.

Height of a pallet stack full of

substrates:

Max. 300mm

Height of an empty pallet stack:

Max. 200mm

Pallets full of

substrates are set

manually. Pallets,

when they become

empty, are unloaded

manually.

Loading unit

(Conveyor type)Conveyor length : 2000mm Optional Substrates are supplied manually.

Unloading unit (Pallet type)Substrates are supplied from pallet.

Height of an empty pallet stack:

Max. 300mm

Height of a pallet stack full of

substrates:

Max. 200mm

Optional

Empty pallets are set

manually. Pallets,

when they become full

of substrates, are

unloaded manually.

Unloading & Conveying

unit 1 set Overhang length of conveyor from

machine : 843mm

Substrates are

unloaded

manually.

Substrate vacuum jig 1 set Special design is required depending on

the substrate type and size.Only one kind of jig is included in the standard specifications.

Edge cleaning unit (Optional)

Base table

X/Y/Z/Į-axis table Substrate vacuum jig Special design is required depending on the substrate type and size.

Wiping cleaning part

Cleaning tape Wiping cloth : width 10 mm•~47 m

(Reel O.D : Max. ƒÓ140mm)

Recommended :

*Savina (Kanebo)

*Toraysee (Toray), etc.

Cleaning head Clamp Force : 4.9 to 19.6N (500•` 2000gf)

Adjustable

Solvent supplier

Supersonic wave air blow ACF laminating unit

Base table

X/Y/Z/Į-axis table 1 set

Substrate vacuum

jig 1 set Special design is required depending on

the substrate type and size.

Only one kind of jig is

included in the

standard

specifications.

Image processing

unit Optional Camera and light

source View: • 7.5 mm Optional

ACF laminating head (Choice of 2 heads is optional)

Constant heater 1 (or 2)Temperature setting : Room

temperature to 150°C

Pressure force9.8 to 196 N (1 to 20 kgf)

Pressurizing time Max. 30 sec.

Co-planarity

adjustment unit 1 (or 2)Manual adjustment by using screw

ACF transfer unit 1 (or 2)Stepping motor

ACF reel size 1 (or 2)Allowable O.D : Max. 125mm.

Half-cut unit 1 (or 2)Only the ACF is cut by the unit, leaving

the base tape uncut.

Peel-off roller 1 (or 2)

ACF laminating guide 1 (or 2)

ACF lamination check

sensor 1 (or 2)Photoelectric switch Pre-bonding unit

Base table X/Y/Z/Į-axis table 1 set

Substrate vacuum

jig 1 set Special design is required depending on

the substrate type and size.

Only one kind of jig is

included in the

standard

specifications.

Camera table

X/Y/Z-axis table 1 set

Image processing

unit 2 sets

Camera and light

source 2 sets View: • 1.2 mm

Bonding head Head elevator (Z) 1 set

Constant heater 1 set Temperature setting : Room temperature to 100°C

Heater face size : Max. 60mm•~6mm

Ceramic heater Temperature setting : Room

temperature to 350°C

Heater face size : Max. 60mm•~6mm

Optional

Pressure force19.6 to 196 N (2 to 20 kgf)

Accuracy: ±4.9 N (±0.5 kgf) Pressurizing time Max. 60 sec.

Co-planarity

adjustment unit 1 set Manual adjustment by using a micrometer.

LSI or FPC loading unit

Pallet stand 1 set LSI or FPC is supplied from pallet.

Height of a pallet stack full of LSI or

FPC:

Max. 300mm

Height of an empty pallet stack:

Max. 200mm

Pallets full of LSI or

FPC are set manually.

Pallets, when they

become empty, are

unloaded manually.

Pick-u p hand jig for LSI or FPC 1 set Special design is required depending on

type and size of LSI or FPC.

Only one kind of jig is

included in the

standard

specifications.

X/Y/Z/Į-Robot 1 set Image processing unit 1 set Camera and light

source 1 set

Slider 1 set Special design is required depending on

type and size of LSI or FPC.Only one kind of jig is included in the standard specifications.

Flip mechanism 2 sets Special design is required depending on

type and size of LSI or FPC.Only one kind of jig is included in the standard specifications.

Supply orientation of

LSI or FPC Face-u p or Face-d ownMain bonding unit

Base table X/Y/Z-axis table 1 set

Backup s tage 2 sets Material: Quartz

Substrate vacuum

jig 2 sets Special design is required depending on

the substrate type and size.

Only one kind of jig is

included in the

standard

specifications.

Camera and light

source View: approx. • 7.5 mm Optional

Backup heater (Constant)Temperature setting : Room

temperature to 150°C

Optional Bonding head

Head elevator (Z) 2 sets

Ceramic heater 2 sets Temperature setting : Room temperature to 350°C

Heater face size : Max. 60mm•~6mm

Pressure force19.6 to 490 N (2 to 50 kgf)

Accuracy: ±4.9 N (±0.5 kgf) Pressurizing time Max. 60 sec.

Co-planarity

adjustment unit 2 sets Manual adjustment by using a micrometer.

Cleaning tape feeder 1 set *Teflon tape for COG and COF Nitoflon (Nitto Denko)

Width 15 mm•~thickness 0.05mm•~30 m

Control unit

Controller 1 set

Touch panel monitor 1 set

Image processing unit

(for alignment) 1 set

CRT monitor

(for image processing) 1 set

Pocket console 1 set

Options

Dispenser Optional

Top cover Optional

HEPA filter Optional

Ionizer Optional2-6. Equipment engineering conditions

1)Jig sets corresponding to application or size of LCD, LSI or FPC are required.

Toray shall prepare the following jigs applied for only one kind of work component which will be used for acceptance test. Jigs for other work components, if required, shall be subject to additional cost on customer.

Unit Jigs to be prearranged Remarks

Substrate vacuum jigs In changing application (from COG, FOG to COF) or size of LCD.

Substrate transfer unit

FPC support jigs In changing application

(from COG, COF to FOG)

Edge cleaning unit Substrate vacuum jig In changing application

(COG, FOG to COF)

Substrate vacuum jig In changing application

(from COG, FOG to COF)

Backup stage or spacer In changing application

(from COG, FOG to COF) ACF laminating unit

Guide roller of ACF In changing ACF width

Heat tool attachment In changing size of LSI or FPC

FPC support jig In changing application

(from COG, COF to FOG)

Backup stage or spacer In changing application

(from COG, FOG to COF) Pre-bonding unit

Substrate vacuum jig In changing application

(from COG, FOG to COF)

Pickup jig In changing size of LSI or FPC

Vacuum jigs for slider In changing size of LSI or FPC

Trays and Pallets In changing size of LSI or FPC LSI/FPC loading unit

Vacuum jigs for flipping In changing size of LSI or FPC

Heat tool attachments In changing size of LSI or FPC

FPC support jigs In changing application

(from COG, COF to FOG)

Backup stages or spacers In changing application

(from COG, FOG to COF) Main bonding unit

Substrate vacuum jigs In changing application

(from COG, FOG to COF)

2) Clean condition of the equipment shall depend upon a clean room and the equipment topside

shall not be covered. Parts and components specifically required for clean room are not used

for the equipment.

3) In case of emergency, main power supply will be turned off. Restarting of the equipment becomes possible after eliminating a cause of the emergency stop and then closing

the operation door for which interlock system is working.

4) During pre-bonding, it is required to make sure that the ACF tape does not stick

to the heated tool.2-7. List of delivery items to customer

Items with asterisk only will be delivered to customer as standard delivery items.

Unit/component Quantity Remarks *Substrate loading unit (pallet type) 1 set

Substrate loading unit (conveyor type)Optional 1

Ionizer Optional 2*Substrate transfer unit 1 set

Edge cleaning unit Optional 3

Ionizer Optional *ACF laminating unit (1 ACF head) 1 set

ACF laminating unit (2 ACF heads)Optional

Alignment CCD camera Optional 4

Ionizer Optional *Pre-bonding unit 1 set

Ceramic heater Optional 5

Ionizer Optional *LSI/FPC loading unit 1 set

*Flip mechanism 2 sets

6

Ionizer Optional *Main bonding unit 1 set

Alignment CCD camera Optional

Backup heater Optional 7

Ionizer Optional

Substrate unloading unit (pallet type)Optional 8

*Substrate unloading unit (conveyor type) 1 set

9Vacuum pump Optional

10HEPA filter Optional

11Top cover Optional

*Transfer jig for large-sized LCD

(from 48mmX48mm to 130mmX130mm) 1 set

12

Transfer jig for small-sized LCD

(from 27mmX27mm to 48mmX48mm)Optional

13*LCD vacuum table

(ACF laminating, Pre-bonding, Main bonding) 1 set

14*LSI pick-up hand with rubber nozzle

(R3-34)

1 set

*Vacuum jig for flipping

(LSI : t = 0.35mm•`0.5mm)2 sets

Vacuum jig for flipping

(LSI : t = 0.5mm•`0.65mm)Optional

Vacuum jig for flipping

(LSI : t = 0.65mm•`0.8mm)Optional 15

Vacuum jig for flipping

(LSI : t = 0.8mm•`0.95mm)

Optional

16Special jigs for change-over to FOG

Model no: TBD Optional

17Special jigs for change-over to COF

Model no: TBD OptionalLSI pallet for 2 or 3 inch tray Optional 18

LSI pallet for 4 inch tray Optional

19LCD pallet

Model no: TBD Optional3. Division of responsibilities

3-1. Responsibilities belonging to TORAY

1) Design, manufacture of equipment and packing

2) Piping, wiring, and painting inside equipment.

3) Acceptance test runs and adjustments.

4) Submission of following documents

a. S pecifications for customer's approval, before order confirmation:

Regular paper 3 copies, 1 copy is for returning to Toray as proof of

approval

b. Documents, to be prepared before shipment:

l Drawings (Equipment overview, wiring diagrams, jigs etc.)

Regular paper 1 copy

l User’s m anual

Regular paper 2 copies

Dust-free paper 1 copy

l Maintenance manual

Regular paper 2 copies

Dust-free paper 1 copy

l List of recommended spare parts

Regular paper 1 copy

3-2. Responsibilities not belonging to TORAY

1) Formalities to competent authorities

2) Wiring works for the sections between the equipment and customer's operation panel

3) Design and installation of piping between the equipment and customer's facility

4) Utility supply works to the equipment.

5) Primary wiring works concerning installation of the equipment, and installation

works

including maintenance work, etc.

6) Preparation of machinery for on-site works (crane, fork-lift, etc.)

7) Condition settings and teaching for production

8) Preparation of spare parts and consumables

9) Shipping and overseas transportation

10) On-site installation

11) Adaptation to CE and UL requirements

12) Bonding quality

13) Matters other than those prescribed in the above

3-3. Customer’s supplies

1) Work components for use in on-site test run and adjustment : Min. 2000 sets

l LCD: Min. 1000 pcs (for COG application)

l LSI : Min. 1000 pcs (for COG application)

l LCD pallet :30 sets (for COG application)

l Chip tray: Quantity equivalent to that of LSIs (for COG application)

l ACF: 2 pcs. (over 20m/1pc) (for COG application)

l Teflon tape : 4 pcs (Nitoflon : Nitto Denko) 15mm X 0.05mm X 30m

* Customer is required to send to Toray the necessary number of work

components for use in adjustment of equipment, no later than one month

before the first day of Initial Acceptance Test.

* The operating efficiency can be checked only if the necessary number of

work components for use in adjustment has been prepared in time. If

they have not been prepared, the operating efficiency check is excluded

from the acceptance conditions.

2)Drawings of work components for the acceptance test

l LCD (for COG application)

l LSI (for COG application)

l L CD pallet (for COG application)

l•@LSI tray (for COG application)

* Customer i s required to send to Toray the drawings of work components

within a week after the order has been received to confirm the

specifications. It is to be noted that the cost of any modification of the

work components, done after the designing process has begun, shall be

additional charge to the customer.

3-4. Others

1) This specification has been prepared and the machine has been manufactured

based on JIS (Japanese Industrial Standards), TES (Toray Engineering

Standards) and Mechanical Equipment Safety Standards, and not based on any

safety standards outside Japan. Accordingly, a dditional cost for any alterations

or additions, if required, shall be borne by customer. Toray, however, shall be

prepared to pay attention to such modification needs which are understood as

caused by the difference s between Toray's standards (JIS, TES, etc.) and other

standards outside Japan, and Toray shall direct its best efforts to find some

practical solutions, with additional cost charged to customer.

2) Arrangements shall be made by customer so that Toray's supervisory work may

be carried out at the customer's site irrespective of existing facility conditions

and that on-site test runs and adjustment works may be performed

continuously without any period of interruption.

3) Customer's personnel in charge are also supposed to participate in the test runs and

adjustments, at all times from its outset.

4) All the costs related to work components to be used in on-site test run and

adjustment shall be borne by the customer.4. Acceptance conditions

When the acceptance test performed at Toray factory with customer personnel in

charge as witness, using one type of work components, result in a satisfactory

confirmation by customer of the equipment meeting acceptance conditions as

described in the following, the equipment will be shipped out of Toray factory. Also,

when it is confirmed that the equipment has been completely reassembled at the

customer's site and that it performs as it was in the initial acceptance test at Toray

factory, the final acceptance test at customer's site is considered complete.

The customer is responsible for the teaching for the different types of work

components. If customer requests that Toray do the teaching or supervisory work

for such different types of work components, the cost incurred will be additionally

charged.

The basic criterion for equipment acceptance is guaranteed mechanical accuracy.

If any problem should occur due to work component and the equipment

specifications consequently need to be modified, engineering cost associated with

the modification will be charged to the customer.

Responsibility shall not be borne by Toray for the products that will be

manufactured using the equipment. If customer requests that Toray engineers

supervise the customer's operation up until proper processing set-up, additional

cost will be charged.

4-1. Alignment accuracy

With one kind of work component for acceptance test, data shall be collected 125

times in verification mode program and specification accuracy shall be verified in

+/-3ƒÐ. With a view to eliminating any factor which could be caused by mark

errors and shifting on bonding, measurement will be repeated for the same

customer's work component without bonding.

4-2. Cycle time

Cycle time (component supply and replacement time excluded) shall be measured,

under process conditions as specified in the cycle time column of the clause 2-3.

on Equipment capability and with the work components used for the acceptance

test.

10 cycle tests are performed and their mean time is calculated. This mean time

value shall be the cycle time.

4-3. Operating efficiency check

In a single hour operation, the interruption rate must be within 5% from the

following calculation. The work component supply time and the interruption time

caused by a work component problem, however, are not included in the machine

interruption time.

Interruption rate (%) =

Machine interruption time – (Product component supply time + Interruption time caused by work component problem)

Actual operation time (1 hour) × 100

*If there are no work components in time for checking the above operating

efficiency, the operating efficiency check is excluded from the acceptance

conditions.

5. Warranty coverage

In case of technical trouble if and when occurring under proper operation

conducted in accordance with the User's manual, Toray warrant that remedial

actions be taken as prescribed in the following, provided that Toray shall be

relieved of responsibilities for any unpredicted damages caused by elements

beyond the control

of Toray after the delivery of the equipment to customer site.

5-1. Warranty period

Should there be any defects of the delivered equipment in design or workmanship,

obviously attributable to the responsibility of Toray, found within one (1) year or

within 3,000 hours of operation( if hour meter is provided), whichever comes first,

after delivery to customer, in spite of proper handling by customer in accordance

with the User's manual, Toray shall repair them or deliver substitutes for the

equipment

or parts, free of charge. Recycled articles and consumables, however, shall be

excluded from the warranty. Besides the above, Toray shall be relieved of

responsibilities for any damages caused by equipment shutdown and any

defective articles caused by equipment failure.

5-2. Supply of maintenance part

Maintenance parts, required to maintain the equipment’s performance and

functions, including compatible equivalents, shall be available for seven years

from the time when the equipment has been handed over to the customer.

5-3. Troubleshooting

As basic support for customer inquiries for any problems, communicating by

telephone or facsimile shall precede and then replacement parts

necessary for maintaining the mechanical functions and overall performance of

the equipment shall be sent to customer. If the problem cannot be solved by such

a basic support, Toray engineer will be dispatched to customer’s factory for

troubleshooting.

5-4. Limit of responsibility

No responsibility or liability shall be assumed for:

l any damage caused by the equipment falling or being dropped during

installation at the customer’s site, or by natural disasters or fire once the

equipment has been installed;

l the quality of products manufactured by the equipment;

l any damage caused by equipment stoppage or the production of defective

products due to a problem with the equipment;

l any loss resulting from a delay in equipment delivery;

l any damage, problem or accident resulting from wrongful use of the equipment

(refer to warnings and cautions in the Users manual), or from any operation not

stipulated in the manual;

l any modification performed without Toray written permission;

l any legal problem regarding the unauthorized re-sale, appropriation, or export

of the equipment, and maintenance required as a consequence of any of these

acts;

l any damage or loss caused to the customer related to third party owned

industrial property rights (regardless of country) of the equipment;

l any fault or accident resulting from improper storage or operation of the

equipment (conditions contradictory to those stated in the specifications);

l any alteration of equipment specifications or delivery date, which have not been

mutually confirmed by the customer and Toray at the time of Toray's order

acceptance;

l the contents of the “Limit of responsibility” and “Responsibilities not belonging

to Toray” sections of this specification document.

6. Handling

For the safe use of the equipment under appropriate conditions, the following

points are requested to be observed by customer.

1) Handler

Only persons who have attended and mastered the training course on proper

handling of the equipment, or who have acquired such skills from a person so

trained, are permitted to operate the equipment.

2) Management

To maintain proper performance and safety requirements, customer’s upkeep

of the equipment must be in accordance with the instructions noted in the

User's manual.

3)Other precautions

l In the event of an emergency stop, the power to moving parts, such as a

servomotor, is turned off. The equipment can be re-started once the cause

of the emergency stop has been remedied and all covers (with interlocks)

has been closed.

l Inappropriate teaching or maintenance work may lead to a dangerous

situation. It is requested that the customer read thoroughly and

understand fully all the contents of the User's manual before beginning

teaching or maintenance.

l Substrates must have no dimensional deviations or curvatures that could

adversely affect their transfer in the equipment.下载本文

显示全文
专题