建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 1 | 010********1 | 平整场地 1.土方平整2.场地找平3.土的运输 | ㎡ | 551.37 | S=首层建筑面积 S=46.5×(6.58+1.68+2.42+0.12+0.1)+(0.12+3.96+0.12)×(5.28-0.1+0.12)×2=551.37 |
| 2 | 010101002001 | 挖土方 1.排地表水、土方开挖2.支挡土板3.基底钎探4.土的运输 | m³ | 634.08 | V=S首层建筑面积×h(室外地坪标高-垫层底标高) V=551.37×(-0.600+1.750)=551.37×1.15=634.08 |
| 3 | 010********* | 土方回填 1.回填土、石方2.分层碾压、夯实3.装卸运输 | m³ | 329.88 | V=V挖-V混 V=634.08-224.87-43.78-35.55=329.88 |
| 4 | 010********* | 填充墙 240厚砖墙//1.M7.5水泥砂浆制作、运输2.砌砖3.装填充料4.勾缝5.材料运输 | m³ | 567.54 | V=(首层+二~五层 +六顶 + 屋顶) ×(墙长×墙净高-嵌入墙身门窗洞口面积)×墙厚;V1(首层)=[(6.58-0.12-0.38-0.38+1.68)×3.2×5+(46.5-0.12-0.12-0.28-0.28-0.4×9)×3.5+(46.5-0.12-0.28-0.4×8-0.2-3.38-0.12)×3.5+(2.42-0.12-0.2)×3.45+2.42×3.5+(2.42-0.12-0.2)×3.5+(3.38-0.23)×3.45+(1.68+6.58-0.38-0.38)×3.2+3.38×3.6+(5.28-0.2-0.28)×3.4×4+(3.96-0.23-0.23)×3.5×2+2.88×3.6-2.6×(3.38-0.2-0.28)-2.1×1×2-2.1×1×2-1×3.5×9-1.5×3.5-2.1×2.55×9-3.6×2.55×8-2.1×1.7] ×0.24=94.79;V2(二~五层)= [(6.58-0.12-0.38-0.38+1.68)×3.2×5+(46.5-0.12-0.12-0.28-0.28-0.4×9)×3.5+(46.5-0.12-0.28-0.4×8-0.2-3.38-0.12)× |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 3.5+(2.42-0.12-0.2)×3.45+2.42×3.5+(2.42-0.12-0.2)×3.5+(3.38-0.23)×3.45+(1.68+6.58-0.38-0.38)×3.2+3.38×3.6+(5.28-0.2-0.28)×3.4×4+(3.96-0.23-0.23)×3.5×2+2.88×3.6-2.6×(3.38-0.2-0.28)-2.1×1.85×2-1.2×0.9×4-2.1×1×2-1×3.5×9-1.5×3.5-2.1×2.55×9-3.6×2.55×8-2.1×1.7] ×0.24×4=371.6;V3(六层)=[(6.58-0.12-0.38-0.38+1.68)×3.25×3+(46.5-0.12-0.12-0.28-0.28-0.4×9)×3.25+(46.5-0.12-0.28-0.4×8-0.2-3.38-0.12)×3.5+(3.38-0.23)×3.45+(2.42-0.12-0.2)×3.5+2.42×3.5+3.38×3.6+2.88×3.6+(5.28-0.2-0.28)×3.4×4+(3.96-0.23-0.23)×3.5×2-2.9×2.6-2.1×1.85×2-1.2×0.9×4-1×2.1×2-1.5×3.5×4-1×3.5-1.5×3.5-2.1×2.55×5-3.6×2.55×12-2.1×1.7] ×0.24=69.82;V4(屋顶)=[(5.28+2.42-0.4-0.28) ×3.4×4+(3.96-0.23-0.23) ×3.5×2+3.96×3.5×2-2.1×1.85×2-1.2×0.9×4-1.2×2.1×2] ×0.24 =31.33;V=V1+V2+V3+V4=567.54 | |||||
| 5 | 010302001001 | 女儿墙 120厚砖墙///1.M7.5水泥砂浆制作、运输2.砌砖3.装填充料4.勾缝5.材料运输 | m³ | 29.68 | V=截面面积×长度 V=(0.84×0.24+0.34×0.12)×(46.26-0.28+8.26+2.42-0.2+8.26+2.42-0.2-0.5-0.38+46.5-1.2-1.2-0.12 -3.96-0.12-0.12-3.96-0.12-0.23)+0.5×0.24×[(2.24+5.28-0.4-0.28)×4+(3.96-0.23-0.23) ×2+3.96 ×2]=29.68 |
| 010********2 | 走廊栏板墙(同上,砌120厚) | m³ | 19.54 | V=截面面积×长度 V=(0.12+0.88)×0.12×(46.5-1.2-2.9-1.2-4.2-4.2-0.23)×5=19.54 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 6 | 010********* | C25基础 1.混凝土浇筑、振捣、 养护 | m³ | 224.87 | V=S1基础面积×h1高度+S2基础面积×h2 V=VZJ1×2+ VZJ2×10+ VZJ3×4+ VZJ4+ VZJ5+ VZJ6+ VZJ7×4+ VZJ8+ VZJ9+ VZJ10+ VZJ11 =(1.5×2.9×0.45+0.9×2.3×0.45)×2+(4.6×3×0.45+2.6×2×0.45)×10+(4.2×2.7×0.45+ 2.4×1.5×0.45)×4+(3.1×2×0.45+2.8×1.2×0.45)+(3×6.3×0.45+1.8×4.8×0.45)+(5.4 ×3.4×0.45+4.4×2.4×0.45)+(3.5×2.3×0.45+1.8×1.3×0.45)×4+(5.7×4.9×0.45+5.3×3.5 ×0.45)+(6×3.7×0.45+4.5×2.2×0.45)+(5.7×3.6×0.45+4.3×2.2×0.45)+(5.2×2.8×0.45 +4×1.6×0.45)=224.87 |
| 7 | 010********* | C10垫层 1.100mm厚素混凝土浇筑、振捣、养护 | m³ | 43.78 | V=S基础垫层面积×h垫层厚度 V=VZJ1×2+ VZJ2×10+ VZJ3×4+ VZJ4+ VZJ5+ VZJ6+ VZJ7×4+ VZJ8+ VZJ9+ VZJ10+ VZJ11 =(0.1+2.9+0.1)×(0.1+1.5+0.1)×0.1×2+(0.1+3+0.1) ×(0.1+4.6+0.1) ×0.1×10+(0.1+2.7+0.1) ×(0.1+4.2+0.1) ×0.1×4+(0.1+3.1+0.1) ×(0.1+2+0.1) ×0.1+(0.1+3+0.1) ×(0.1+6.3+0.1) ×0.1+ (0.1+5.4+0.1) ×(0.1+3.4+0.1) ×0.1+(0.1+3.5+0.1) ×(0.1+5.3+0.1)×0.1×4+(0.1+5.7+0.1) ×(0.1+4.9+0.1)×0.1+(0.1+6+0.1)×(0.1+3.7+0.1)×0.1+(0.1+5.7+0.1)×(0.1+3.6+0.1) ×0.1+(0.1+5.2+0.1) ×(0.1+2.8+0.1) ×0.1=43.78 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 8 | 010********* | C25矩形柱 1.混凝土浇筑、振捣、养护 | m³ | 183.05 | V=S柱截面积×h柱高(基础上皮至顶层柱顶)×根数 V=VKZ1[0.4×0.5×(23.35+0.75)]+VKZ2[0.4×0.5×(23.35+0.75)]+VKZ3[0.4×0.5×(23.35+0.75) ] +VKZ4[0.4×0.5×(23.35+0.75)]+VKZ5[0.4×0.6×(3.85+0.75)+0.4×0.5×(23.35-3.85)] ×6+VKZ6[0.4×0.6×(3.85+0.75)+0.4×0.5×(23.35-3.85)] ×3+ VKZ7[0.4×0.6×(3.85+0.75) +0.4× 0.5×(23.35-3.85)] ×2+VKZ8[1.2×0.3×(28+0.75) ]×2+VKZ9[0.35×0.4×(26.35+0.75)] ×4+ VKZ10[0.35×0.4×(26.35+0.75)] ×4+VKZ11[0.4×0.6×(3.85+0.75)+0.4×0.5×(23.35-3.85)] + VKZ12[0.4×0.6×(3.85+0.75)+0.4×0.5×(23.35-3.85)+0.25×0.25×(26.35-23.35) +VKZ13[0.4× 0.6×(3.85+0.75)+0.4×0.5×(23.35-3.85)+0.25×0.25×(26.35-23.35)+VKZ14[0.4×0.5×(23.35+ 0.75)]+VKZ15[0.4×0.5×(23.35+0.75)]+VKZ16[0.4×0.5×(25.8+0.75)]+ VKZ17[0.4×0.5×(25.8+ 0.75)]+VKZ18[0.35×0.4×(25.8+0.75)]+0.25×0.35×(26.35+0.05) ×4+0.25×0.25×(26.35-23.35) ×4=183.05 |
| 9 | 010********* | C25基础梁 1.混凝土浇筑、振捣、养护 | m³ | 35.55 | V=S截面面积×L长度 V=VKL6[0.3×0.7×(46.5-11×0.4)]+VKL7[0.3×0.7×(46.5-11×0.4)]+VKL1[0.25×0.7×(6.58+ 1.68+2.42-0.2-0.5-0.38) ×2+VKL8[0.3×0.7×2.9]+VLL2[0.25×0.3×(2.88-0.125-0.125)] +VKL2 [0.25×0.7×(6.58+1.68-0.48-0.48) ×3]+VKL4[0.25×0.7(6.58+1.68-0.38-0.38)]+VKL5× [0.25× |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 0.7×(6.58+1.68-0.38-0.38)]+VLL1[0.25×0.3×(3.38-0.125-0.125)+VKL3[0.25×0.7×(2.42+5.28- 0.15-0.4-0.35-0.28) ×4]+VKL9[0.25×0.7×(3.96-0.23-0.23) ×2]+VKL10[0.25×0.7×(3.96-0.23- 0.23) ×2]=35.55 | |||||
| 10 | 010********* | C25矩形梁 1.混凝土浇筑、 振捣、养护 | m³ | 117.4 | V=S截面面积×L长度 V=V二层梁+V三~六层梁+V屋面梁 V={VKL1[0.25×0.4×(3.96-0.23-0.23) ×2+VKL2[0.25×0.7×(6.58+1.68-0.38-0.38) ]+VKL3[0.25 ×0.7×(6.58+1.68-0.38-0.38)]+VKL4[0.25×0.65×(6.58+1.68-0.48-0.48)]+VKL5[0.25×0.7×(6.58 +1.68-0.48-0.48) ×2 ]+VKL6[0.25×0.5×(5.28-0.2-0.35-0.28) ×4]+VKL7[0.25×0.65×(6.58+1.68 -0.48-0.48) ×2]+VKL8[0.25×0.65×(6.58+1.68-0.48-0.48)]+VKL9[0.25×0.7×(6.58+1.68-0.48 -0.48)]+VKL10[0.25×0.7×(6.58+1.68-0.38-0.38)]+VKL11[0.25×0.7×(6.58+1.68-0.38-0.38)]+ VKL12[0.3×0.4×(46.5-11×0.4)]+VKL13[0.3×0.4×(46.5-11×0.4)]+VKL14[0.2×0.45×(46.5-1.2 -1.2-0.35×5)]+VLL1[0.25×0.3×(3.38-0.125-0.125)+VLL2[0.25×0.3×(2.28-0.125-0.125)+VLL3 [0.25×0.4×(3.96-0.125-0.125) ×2]+0.25×0.45×(2.42-0.2-0.12) ×7+0.25×0.4×(2.42-0.2-0.12 )×5}+{VKL1[0.25×0.4×(3.96-0.23-0.23) ×2+VKL2[0.25×0.7×(6.58+1.68-0.38-0.38) ]+VKL3 [0.25×0.7×(6.58+1.68-0.38-0.38)]+VKL4[0.25×0.65×(6.58+1.68-0.38-0.38)]+VKL5[0.25×0.7× (6.58+1.68-0.38-×2 ]+VKL6[0.25×0.5×(5.28-0.2-0.35-0.28) ×4]+VKL7[0.25×0.65×(6.58+1.68 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| -0.38-0.38) ×2]+VKL8[0.25×0.65×(6.58+1.68-0.38-0.38)]+ VKL9[0.25×0.7×(6.58+1.68-0.38 -0.38)]+VKL10[0.25×0.7×(6.58+1.68-0.38-0.38)]+VKL11[0.25×0.7×(6.58+1.68-0.38-0.38)]+ VKL12[0.3×0.4×(46.5-11×0.4)]+VKL13[0.3×0.4×(46.5-11×0.4)]+VKL14[0.2×0.45×(46.5-1.2 -1.2-0.35×5)]+VLL1[0.25×0.3×(3.38-0.125-0.125)+VLL2[0.25×0.3×(2.28-0.125-0.125)] +VLL3 [0.25×0.4×(3.96-0.125-0.125) ×2]+0.25×0.45×(2.42-0.2-0.12) ×7+0.25×0.4×(2.42-0.2-0.12 )×5}×4+ VW KL1[0.25×0.4×(3.96-0.23-0.23) ×2+VWKL2[0.2×0.45×(46.5-1.2-1.2-0.35×5)] + VWKL3[0.25×0.65×(6.58+1.68-0.38-0.38)]+VWKL4[0.25×0.65×(6.58+1.68-0.38-0.38)]+ VWKL5[0.25×0.65×(6.58+1.68-0.38-0.38) ×2]+VWKL6[0.25×0.65×(6.58+1.68-0.38-0.38) ×2 ]+VWKL7[0.25×0.5×(5.28-0.2-0.35-0.28) ×4]+VWKL8[0.25×0.65×(6.58+1.68-0.38-0.38) ]+ VWKL9[0.25×0.65×(6.58+1.68-0.38-0.38) ×2]+ VWKL10[0.25×0.65×(6.58+1.68-0.38-0.38)]+ VWKL11[0.25×0.7×(6.58+1.68-0.38-0.38)]+VWKL12[0.25×0.65×(46.5-11×0.4)]+VWKL13 [0.25×0.4×(46.5-11×0.4)] +VWLL1[0.25×0.4×(3.96-0.125-0.125) ×2]+VWLL2[0.25×0.3× (3.38-0.125-0.125)]+VWLL3[0.25×0.3×(2.28-0.125-0.125)]+ 0.25×0.45×(2.42-0.2-0.12) ×2+ 0.25×0.55×(2.42-0.2-0.12) ×5+0.25×0.4×(2.42-0.2-0.12) ×4+0.3×0.45×(2.42-0.2-0.12) +0.25 ×0.4×(3.96-0.23-0.23) ×2+0.25×0.5×(2.42+5.28-0.125-0.4-0.2) ×4+0.25×0.45×(3.96+1.615+ 1.615+0.1+0.1-0.25-0.25) ×2+0.25×0.45×(3.96+1.615+1.615+0.1+0.1-0.4-0.4) ×2+0.2×0.45× (2.42+5.28-0.125-0.125) ×4+0.2×0.45×(1.615-0.1-0.125) ×16=117.4 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 11 | 010********* | C25女儿墙及阳台 压顶圈梁1.混凝土浇筑、振捣、养护 | m³ | 4.15 | V=S截面面积×长度 V=0.1×0.24×(7.58×2+3.96×2)×2+0.1×0.24×(46.5-0.12-0.12+8.26+2.42-0.12-0.2+8.26+2.42 -0.12-0.38-0.5-0.2+46.5-1.2-1.2-4.2-4.2-0.23)+0.1×0.24×(3.38-0.2-0.28+1.68-0.38) ×6=4.15 |
| 12 | 010403005001 | C25现浇混凝土过梁 1.混凝土浇筑、振捣、 养护; | m³ | 1.78 | V=S截面面积×长度(0.24+ L +0.24)h=0.12 V=0.24×0.12×[(0.24+1+0.24)×2×6+(0.24+1.2+0.24) ×4×6+(0.24+1.2+0.24)×2]=1.78 |
| 13 | 010405001001 | C25现浇楼板 1.130厚混凝土浇筑、振捣、养护 | m³ | 235.05 | V=长×宽×板厚 V=(5-0.125-0.125) ×(6.58+1.68-0.18-0.15) ×8×0.13×6=235.05 |
| 010********2 | C25现浇楼板 1.100厚混凝土浇筑、振捣、养护 | m³ | 93.45 | V=长×宽×板厚 V=[(6.58+1.68-0.15-0.25-0.18)×(2.88-0.13-0.125)+(2.42-0.15-0.2) ×(46.5-0.25×11)+(3.96- 0.125-0.125) ×(1.8-0.125-0.125) ×2+(3.38-0.125-0.125) ×(6.58+1.68-0.15-0.25-0.18)] ×0.1×6 +(2.42+5.28-0.25-0.25)×(4.2-0.25)×0.1×2=93.45 | |
| 14 | 010********* | C25直形楼梯 1.1.楼梯基础2.零星砌砖3.混凝土浇筑振捣、养护 | ㎡ | 74.79 | S=楼梯长×楼梯宽×层数 S=3.36×(3.96-0.125-0.125)×6=74.79 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 15 | 010********* | 散水 60厚C15混凝土垫层,面上加5厚1:1水泥砂浆面层随打随抹//60厚砂垫层//素土夯实,向外坡4%1.混凝土制作2.基础垫层铺设3.沥青砂浆嵌缝68.62m | ㎡ | 63.31 | S=长×宽 S=(0.9+46.5+0.9+0.12+1.68+6.58+2.42+3.38-0.15+0.9+6.58+1.68-0.15+0.12)×0.9=63.31 |
| 16 | 010********* | 台阶 60厚C15混凝土垫层 (厚度不包括踏步三角部分),面上加5厚1:1水泥砂浆面层//素土夯实//1.混凝土制作2.台阶基础或筋墙砌砖 | ㎡ | 32.69 | S=水平投影面积=长×宽 S=(46.5-3.38+0.23+0.35+0.35+2.42+0.23)×(0.35+0.35)=32.69 |
| 17 | 010********* | 屋面卷材防水 粘结蛭石或云母保护层//4mm厚SBS改性沥青防水卷材//刷基层处理剂一道//20厚1:6水泥加气混凝土找坡2%//20厚1: | ㎡ | 434.1 | S=长×宽 S=(6.58+1.68-0.12-0.12)×(46.5-0.12-0.12)+(3.38-0.12-0.12)×2.42+(3.96-0.12-0.12)×( 2.42+5.28-0.12-0.12) ×2=434.1 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 3水泥砂浆找平层//1.铺油毡卷材、接缝、嵌缝2.基层处理3.抹找平层4.刷底油5.铺保护层 | |||||
| 18 | 010702004001 | 屋面出水口 1.DN110出水嘴及配件安装2.雨水篦子安装8个,接缝、嵌缝 | 个 | 8 | 图纸标注数量 |
| 19 | 010********* | 现浇混凝土钢筋 一级D10以内22.29t//一级D10以外39.45t//二级D20以内19.95t//二级D20以外70.3t//1.钢筋制作、安装 | t | 152 | 基础、柱梁板各种规格钢筋计算长度×钢筋理论重量 D10以内:Ø6 5272m ×0.222=1.17t;Ø8 53459m ×0.398=21.12; D10以外:Ø10:3165m ×0.617=1.95t;Ø12 42235m×0.888=37.5t; DN20以内:Ф12:1004×0.888=0.t;Ф14:4015.2×1.21; Ф16:7485m×1.58=11.83t;Ф18:1183m×2=2.37t DN20以外:Ф20:11655m×2.47=28.79t, Ф22: 7534×2.98=22.45t Ф25:4952m×3.85=19.07t |
| 20 | 010********* | 预埋铁件 铁件制作、运输、安装 | t | 1.08 | 埋件 -150×150×8 钢板埋件个数×理论重量 (456+312)×1.41kg/个=1083kg |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 1 | 013102004001 | 双排外脚手架措施费 场内外材料搬运//搭设拆除脚手架//上下翻板子和拆除后的材料堆放 | ㎡ | 4043.95 | 按墙面垂直投影面积计算 S=周长×建筑高度 S=(46.5×2+5.28×4+16.2×2)×27.6=4043.95 |
| 2 | 013103001001 | 现浇混凝土基础模板 木模制作、安装、拆除//支撑安装、拆除整理堆放及场外运输 | m³ | 268.65 | V=V基础混凝土 V=224.87+43.78=268.65 |
| 3 | 013103002001 | 现浇混凝土柱模板措施 木模制作、安装、拆除//支撑安装、拆除整理堆放及场外运输 | m³ | 183.05 | V=V柱 V=183.05 |
| 4 | 013103003001 | 现浇混凝土梁模板措施 木模制作、安装、拆除//支撑安装、拆除整理堆放及场外运输 | m³ | 158.88 | V=V梁 V=35.55+117.4+4.15+1.78=158.88 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 5 | 013103005001 | 现浇混凝土板模板措施 木模制作、安装、拆除//支撑安装、拆除整理堆放及场外运输 | m³ | 328.5 | V=V板 V=235.05+93.45=328.5 |
| 6 | 013103006001 | 现浇混凝土楼梯模板 措施费 木模制作、安装、拆除//支撑安装、拆除整理堆放及场外运输 | m³ | 74.79 | V=V楼梯 V=74.79 |
| 7 | 013103007001 | 现浇混凝土台阶、 散水模板措施费 木模制作、安装、拆除//支撑安装、拆除整理堆放及场外运输 | ㎡ | 196.25 | S=S散水+S台阶 S=63.31+132.94=196.25 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 8 | 013104002001 | 混凝土现场泵送费 混凝土泵送设备运输、安装、调试、移动、维护、拆除 | m³ | 1013.87 | V=V混 V=224.87+43.78+183.05+35.55+117.4+4.15+235.05+93.45+74.79=1013.87 |
| 9 | 013107001001 | 超高工程附加费 多层建筑//建筑物檐高超过20m施工时,由于人工、机械降效所增加 | ㎡ | 2823.55 | 首层地面以上全部建筑面积 S=551.37×5+(2.42+5.28+0.12+0.12)×4.2×2=2823.55 |
| 10 | 013101001001 | 施工排水、降水措施费 集水井(做井、洗井) | 座 | 2 | 基础集水井以座计算 |
| 11 | 013101003001 | 施工排水、降水措施费 抽水(安装水泵、抽水) | 台班 | 抽水以台班计算,当连续昼夜抽水时,一昼夜按3个台班计算 | |
| 12 | 013105001001 | 建筑物垂直运输 各种材料的垂直运输//高层建筑施工用水加压 | 工日 | 以基价子目中不带()总工日计算,凡基价子目的工日有()者不计算 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 13 | 013106001001 | 大型机械设备进出场及安拆费 塔式起重机基础 // 钢筋混凝土基础制作 | 座 | 1 | 固定式基础按座计算 |
| 14 | 013106004001 | 大型机械设备安拆费 自升式塔式起重机//机械运至现场后的安装,试运转,竣工后的拆除 | 台次 | 机械安拆费按施工方案规定的次数计算 | |
| 15 | 013106009001 | 大型机械设备安拆费 混凝土搅拌站//机械运至现场后的安装,试运转,竣工后的拆除 | 台次 | 械安拆费按施工方案规定的次数计算 | |
| 16 | 013106010001 | 大型机械设备进出场费 履带式挖掘机整体或分体自停放地点运至施工现场运输、装卸 | 台次 | 包干运费按施工方案以台次计算 |
建筑工程部分
| 序号 | 清单编号 | 项目名称 | 单位 | 数量 | 计算式 |
| 17 | 013106018001 | 大型机械设备进出场费 自升式塔式起重机整体或分体自停放地点运至施工现场运输、装卸 | 台次 | 包干运费按施工方案以台次计算 | |
| 18 | 013106020001 | 大型机械设备进出场费 混凝土搅拌站整体或分体自停放地点运至施工现场运输、装卸 | 台次 | 包干运费按施工方案以台次计算 | |
| 19 | 文明施工措施费 | 元 | 直接工程费×1.07% | ||
| 20 | 临时设施措施费 | 元 | 直接工程费×1.38% | ||
| 21 | 竣工验收存档 资料编制费 | 元 | 直接工程费×0.10% | ||